Austin’s Energy’s Billing System
Can’t Light Up
Is the Austin
Energy project a failure? Explain your answer.
Yes, the Austin Business Project is failure
because:
Modernization billing project delays -
Austin and IBM project late completion, delay schedule, software bugs.
Complexity new billing system with 73 different interface
Software bugs - Error of thousands of bills,
65000 never received bills35000 in accurate bills, overcharging
Instability issues - Seriously impact
business and customer, Persistent system error from billing department and
Revenue loses
Customer services employee - Employee
response one to one assistant for account accessing and correcting error.
Customer - Unable to access system online
portal and System causes a lot of problem, not friendly and hard time for
customer.
IBM failure - Billing software system
failure
Describe the
business impact of the faltering Austin Energy project.
Operation are mostly affected is billing
department.Difficulties of issuing bills because of billing software failure, Common
error of customer not received bills, customer receive in accurate bills, account
automatically cancelled, Incurred more cots in utilities and operation. Since
business function is interconnected, one function failure give impact of another
function such as production, Business service is inaccurate, it give impact in
revenue and profit even though they don’t have pressure of competitor.
Customer servicedepartment mostly
affected.Employee work in high level of stress, Extra effort need to solve
customer problem. They still need to serve customer better even though customer
angry to show their disappointment towards the company, Employee also treated
in the same way as usual, do not receive any appreciation from the company and Give
impact of public relationship disaster.
Sales and marketing such as company also faced difficulties in
determining the actual sales since the system leads more error, Sales and
profit decreasing, Company might face law suit for this issues. If it is happening,
more cost to handle legal costs. It is bad for company since give negative
impact in their legacy and Company also incurred more cost in advertising to
give explanation to the public about what happen.
Finance and accounting such as Inaccurate financial
report since the actual value of revenue and profit inaccurate recorded, give
impact of financial planning and investment and the project is delayed, suppose
fully operational in early 2011 but it still not fully operational and incurred
more cost.
Management will do a wrong decision making
of having IBM to develop the software as the bad experience IBM performance in
inventory management, the service given by IBM is bad and disappointment and need
to train all employees with new technology.
Customer will mostly affected. Whereby System
also not user friendly, Austin portal also always have problem, customer can’t
access account information and company also doesn't think of their preference
such as ability to choose time of the month that customer prefers to pay bills.
To what degree was
IBM responsible for the problems countered by the Austin Energy billing
project? Was Austin Energy at fault for the problems? Explain your answer.
IBM not really responsive to the problems
and it made Austin Energy appealed so many times to IBM officials ranging from
the managers of billing system project up to IBM CEO. IBM responsible in find
the roof of problem, make system correction, test the latest system version and
implement the system.
Yes, Austin Energy is at fault for the
problem. It is because Austin Energy as a user had to be committed to the
system. Probably, Austin Energy did not plan very properly in the project to
develop the billing system. They must have clear and proper project management
objective which should deal with five major variables: scope, time, cost,
quality and risk. The agreement should clearly define the roles and
responsibilities of both party.
What were the
specific organizational or technical factors as well as management factors
involved in this projects failure?
Organizational:Employee could not be
committed enough and described as if they are alpha tester when they
encountered bugs and issues that never have made it to a live version, unable
to meet customer satisfaction, no realignment internally and externally, caused
vastly on costs that exceed budgets, fail to meet customer expectation and lost
trust draws customer away.
Technical:No specific infrastructure, unreliable
system caused money loss, did not work closely with third party vendors like
oracle, customers unable to access the system’s online portal.
Management:No strategy which cause time
slippage, no business solutions, interrelated with manpower, repeating mistakes
and delays and improper project management objective.
Describe the steps
Austin Energy and IBM should have taken be better manage this project.
Austin Energy and IBM need to develop an
information system plan which indicates:
Austin Energy and IBM need to develop an
information system plan which indicates
such as the direction of system development, the rational, the current
system/situation, new development to consider, the management strategy, the
implementation plan and Budget requirement